Core Drilling Cost in Melbourne: What Affects the Price

Core Drilling Cost in Melbourne: What Affects the Price

Core drilling is rarely priced as a single flat number. Published Australian figures put a standard 100mm hole in ordinary concrete at roughly $90 to $130, but the price you actually pay is set by hole diameter, depth, reinforcement, access, scanning and the minimum charge for attending site. We list concrete cutting on our site at $450 to $5,000 for a one-off job, and we quote core drilling per project because the slab, the access and the number of holes decide the total. This guide shows how the price is built, so you can read a quote and give a contractor what they need to price it properly.

Vicsawing
Get a Clear Core Drilling Quote
Share your project details with Vic Sawing & Drilling to discuss core drilling for your Melbourne or Victorian site.

Visit

TL;DR

  • A single 100mm core hole in standard concrete is published at about $90 to $130, but one hole on its own is usually priced as a minimum visit, not per hole.
  • Price rises with diameter, depth, steel reinforcement, tight or elevated access and the number of separate visits.
  • Scanning the slab before drilling is part of a safe, accurate job, and it protects you from the far larger cost of hitting a cable or conduit.
  • Wet drilling and slurry removal are required safety practice for silica dust, so they belong in every quote.
  • The fastest way to a firm price is to send hole sizes, depths, slab type, access details and photos.

Table of Contents

What core drilling is, in one paragraph

Core drilling uses a hollow, diamond-tipped barrel that spins through concrete and removes a clean, round plug (the core). Trades use it for pipes, drainage, electrical and data penetrations, ventilation, anchor and bolt holes, and test holes. Unlike a hammer drill, it leaves a smooth, accurate hole with little vibration, which matters in occupied buildings and near structural elements. If you want the technique explained in more depth, see our guides on what core drilling is and core drilling explained.

Typical core drilling prices in Melbourne and Australia

There is no standard national rate card for core drilling. Published figures come from tool makers, trade calculators and contractor pages, and they differ by region, equipment and the contractor’s own costs. They are best used to sense-check a quote, not to replace one.

Here is what the published figures show:

Item Published figure What it tells you
100mm hole in standard concrete $90 to $130 (Tyrolit Australia, published 8 January 2026) A per-hole range for a common size in unreinforced or lightly reinforced slab
Confined-space access 20 to 30% surcharge on the same hole Access changes the price even when the hole does not
Our concrete cutting jobs $450 to $5,000 one-off, as listed on our site Whole-job pricing for cutting work, depending on scope

Two points follow from this. First, a per-hole figure is only part of the story: the same hole costs more in a basement plant room than on an open ground slab. Second, the more holes in one visit, the lower the average cost per hole, because travel, set-up, water and power connection and clean-up are shared.

Worked example

Say you need six 100mm holes through a ground-floor slab with good access. Using the published $90 to $130 range, six holes come to $540 to $780 before any call-out or set-up charge, scanning, or extra for reinforcement. If the same holes sat in a confined riser and the 20 to 30% access surcharge applied, the hole total would move to roughly $648 to $1,014. These are arithmetic illustrations on a published range, not a quote: your own slab and access will set the real figure.

Worked example of core drilling cost ranges

How core drilling is priced

Contractors use one of four approaches, and a good quote will tell you which.

  1. Per hole, by diameter and depth. The most common for small and medium jobs. Each diameter has its own rate and a minimum depth is charged per hole.
  2. Per unit of depth. Some rate cards charge per 10mm or per metre of depth, with a different rate for each diameter. This suits deep holes through thick slabs, beams or walls.
  3. Per visit plus per hole. A set-up or call-out charge covers getting equipment, water and power to the work area, then each hole is added on top.
  4. Per project. For larger or more complex work, such as many penetrations over several floors, a single project price is built from all of the above plus access and programming.

We quote core drilling per project because the slab, access and number of holes vary so much between sites. That gives you one number for the whole scope instead of a list of rates that can shift as conditions are found on the day.

What makes the price go up or down

Hole diameter

Bigger holes take longer, need larger and more expensive diamond barrels and remove more concrete. Small service penetrations are the cheapest. Large holes for drainage, ducting or stormwater connections cost noticeably more each, and very large openings are usually better handled with wall sawing or ring sawing than with a core barrel.

Depth

Depth drives both time and the cost of the barrel. A 150mm slab is a quick job; a 400mm transfer slab or a thick wall needs more time, extension barrels and more careful slurry control. If your hole is deep, read how deep you can core drill concrete before you finalise the design.

Reinforcement and concrete strength

Steel bar in the path of the barrel slows the cut and wears the segments faster. Concrete strength matters too. Australian Standard AS 1379 sets normal-class strength grades from 20 up to 100 MPa, and according to Tyrolit Australia, reinforced concrete above 40 MPa wears cheaper carbide bits out in only 5 to 10 holes, while diamond segments handle it better. High-strength, heavily reinforced slabs are priced higher for exactly this reason.

Access and working position

Overhead drilling, tight plant rooms, risers, basements, work from scaffolding or lifts, and long runs for hoses and cables all add time. Floor-level work on an open slab is the baseline. Tell your contractor early if the drilling is above head height or in a confined area, because that is where the access surcharge applies.

Scanning before drilling

Unknown slabs can hide post-tension cables, conduits, plumbing and reinforcement. Scanning with ground penetrating radar (GPR) shows what is inside the concrete so holes can be positioned safely. It adds a modest line to the quote, but it avoids the far larger cost of cutting a stressed cable or a live service. Our article on the importance of GPR concrete scanning explains what a scan shows and when it is worth doing. A scan helps locate hazards but does not by itself certify that a spot is structurally safe: for structural elements, the responsible engineer signs off on the hole location before drilling.

Number of holes and visits

Every attendance has fixed costs: travel, setting up, connecting water and power, protecting finishes and cleaning up. One hole and twenty holes cost nearly the same to set up. That is why minimum charges exist and why grouping all your penetrations into a single visit is the single easiest way to bring the cost per hole down.

Dust, water and clean-up

Cutting concrete releases respirable crystalline silica, a hazardous dust. The WorkSafe Victoria industry standard for safe concrete cutting and drilling calls for wet methods to minimise dust and for slurry to be removed before it dries, so it cannot become airborne. Where water is not practicable, it points to dust extraction and other controls. Water supply, slurry collection and extraction are therefore part of the real cost of doing the job properly, and a quote that leaves them out is incomplete.

Minimum charges and why one hole costs more than you expect

Homeowners and property managers are often surprised that a single hole is quoted at several times the per-hole rate. The reason is simple: the time and equipment needed to attend, set up and finish are the same whether the job is one hole or ten. Published Australian trade calculators reflect this with minimum job and call-out fees rather than a pure per-hole price. Our own concrete cutting work is listed at $450 to $5,000 for a one-off job, which gives a sense of the range once scope is taken into account.

If you only need one or two holes, ask whether other small jobs on the property can be bundled into the same visit, such as a drain penetration, a bolt-down hole or a section of hand sawing. That spreads the fixed cost across more work.

How long core drilling takes

A small hole through a standard slab takes minutes of drilling time. The rest of the visit is set-up, water and power, positioning, scanning if needed, and clean-up. Time grows with:

  • depth and reinforcement, which slow the barrel
  • access problems, such as confined or overhead work
  • the number of holes and how far apart they are
  • the need to protect finishes, isolate services or work outside business hours

Because time is what you are paying for, a job with clear drawings, marked hole locations and clear access runs faster and costs less.

What to send to get an accurate quote

Vague enquiries get wide price ranges. These details let a contractor give a firm number:

  1. Number of holes and whether they are in one location or spread across floors.
  2. Diameter and depth of each hole, or at least what passes through it (pipe size, duct size, anchor type).
  3. Material and thickness: slab, wall, beam, footing, and whether it is reinforced or post-tensioned.
  4. Access: floor level, basement, riser, overhead, lift availability, parking and distance to water and power.
  5. Photos and drawings of the area, including slab drawings and the proposed penetration details where you have them.
  6. Timing and site rules: after-hours work, induction requirements, occupied spaces and noise limits.
  7. Whether the area has been scanned and whether an engineer needs to approve locations.

Keeping drawings, approvals and scan results in one place speeds up quoting and site sign-off. If you manage several trades, a clear construction document control process helps make sure the right drawings reach the contractor.

Comparing quotes fairly

Line up the same things in every quote before comparing totals:

  • Is scanning included, or priced separately?
  • Is a call-out or set-up charge shown?
  • Are diameters and depths stated for every hole?
  • Does the price cover wet drilling, slurry removal and clean-up?
  • Does it allow for reinforcement and for the access you described?
  • Are licensed, qualified operators doing the work, with site safety documentation?

The cheapest total is not the lowest cost if it leaves out scanning, dust control or clean-up that you then pay for separately, or if it leaves you carrying the risk of a damaged cable.

Who gets the best value from professional core drilling

Contractors and builders get clean penetrations on programme, without losing a crew to a job that needs specialist equipment. Property managers get work done with controlled dust, water and noise in occupied buildings. Architects and engineers get holes located from their drawings and signed off before cutting. Industrial facilities get drilling scheduled around shutdowns. Homeowners get a tidy result for a drain, a flue, a clothesline footing or a new service line, with the slab scanned first.

Who gets the best value from professional core drilling

On bigger work, core drilling often sits alongside other methods. Concrete removal, wall sawing, wire sawing and road sawing may be part of the same scope, and one contractor handling all of them removes handovers and reduces the number of mobilisations you pay for. If removal is part of your project, our guide to concrete removal costs in Melbourne sets out the waste rules and a quote checklist.

Our perspective

Core drilling looks simple from the outside: a round hole in a slab. The cost sits in everything around the hole. We scan before we drill, we use wet methods to control silica, and we plan access so the work is done in one visit where possible.

That is why we quote per project instead of handing out a single per-hole figure. The slab, the reinforcement, the access and the number of penetrations all change what the job takes, and a project price lets you see the whole scope up front.

Our operators are licensed and qualified, we work to OH&S safety standards, and we have handled everything from small residential jobs to large commercial construction projects across Melbourne and Victoria. For our clients, the value is a clean, accurate hole in the right place, with the structure and the services behind it left undamaged.

MYBMC

Get a core drilling price for your project

We handle core drilling, concrete scanning, sawing and removal for commercial, industrial and residential projects across Melbourne and Victoria. Send us your hole sizes, depths, slab details and photos and we will price the whole job, with a free quote.

Vicsawing

To discuss your project or request a quote, visit Vic Sawing & Drilling.

FAQ

How much does it cost to core a hole in concrete?

A published range for a 100mm hole in standard concrete is about $90 to $130 per hole, and confined-space access can add 20 to 30%. A single hole is usually charged as a minimum visit because set-up, water, power and clean-up cost the same for one hole or many. A written quote for your slab is the only reliable figure.

Is core drilling priced per hole or per metre?

Both are used. Small and medium jobs are normally priced per hole by diameter and depth, while deep holes may be charged by depth. Larger jobs are often priced per project. We quote core drilling per project so the slab, access and number of holes are all covered in one price.

Why does reinforced concrete cost more to drill?

Steel in the path of the barrel slows the cut and wears the diamond segments faster, and high-strength concrete does the same. That extra time and wear is built into the price. Scanning first shows where reinforcement and services sit so holes can be positioned sensibly.

Do I need to scan the slab before core drilling?

Scanning is strongly advisable whenever the internal layout of the concrete is unknown, since slabs can contain post-tension cables, conduits and plumbing. It adds a small cost compared with the damage a strike can cause. For structural elements, ask your engineer to confirm hole locations before drilling.

What affects how long core drilling takes?

Depth, reinforcement, access and the number of holes set the time, along with set-up and clean-up. Clear drawings, marked locations and good access shorten the visit and lower the cost.

Sources